Coordination
is a word that gets thrown around a lot during a big project. Design has to be
coordinated. Deliveries have to be coordinated. Installation has to be
coordinated. However, when you stuff a bunch of equipment from different
manufacturers in a small area, thats when the rubber hits the road for
coordination.
The
arrival of installation teams from Ferag and Heidelberg to The
Courier-Journals downtown Louisville, Ky., facility signaled the beginning of
the most critical test of coordination in the production facility project.

The
Courier-Journals mailroom already looks full, although more stackers and tie
lines are coming.
Photos: The Courier-Journal
At
the same time, and in roughly the same space, crews from Alvey Systems began the
initial testing of the bundle distribution system, which they tied into a new
cart loader from Cannon Equipment Co.
Ferag,
supplying the gripper conveyors from the Koenig & Bauer press to the
mailroom, arrived in early January and immediately installed the first five
stacker infeed assemblies.
Although
only three SIAs were needed for the first press, two additional SIAs were
required to tie in both lines of Heidelbergs NP632 inserter on schedule.
First
gripper
The
first gripper track to go in was for press 3 (the first press being installed),
and was color-coded red. Although the schedule didnt call for hanging the
track on press 2, Ferags installation manager proceeded to hang the track to
check for interference.
This
turned out to be a wise decision, as one piece of the yellow press 2 track will
have to be slightly modified to fit its spot. Additionally, a minor adjustment
had to be made to the height of some of the SIAs to allow a Quipp Systems Inc.
401 stacker to pass under them. Although the plans showed a full quarter inch of
clearance, field modifications are at times necessary.
Heidelberg
mobilized at the beginning of February, immediately setting the NP632 inserter
in place. To the casual observer, the inserter was nearly installed after only a
few days, but mechanical and electrical connections still needed to be made and
the delivery gripper had to be installed.
Once
the NP632 and its associated conveyors are installed, Heidelberg will move to
the north end of the mailroom and install the remanufactured 1472.
Although
all of the gripper conveyor going in is very interesting, the real star of the
month was Alvey. Its bundle distribution system started on schedule and test
bundles began flowing up the spirals to the overhead accumulation conveyors.
High
speeds
After
the sorter at the cart loaders was tied into Cannon cart loader No. 5, bundles
could flow throughout the system at a rate that is significantly faster than the
theoretical top speed of all three KBA presses running simultaneously.
This
high processing speed, combined with Alveys patented accumulation belt
system, effectively creates an internal buffer system, should any downstream
equipment cause delays in processing.
On
the pressroom side of the plant, BG Industrials ink system was completed and
successfully tested, and technotrans followed along closely to install the
reverse osmosis and dampening systems.
KBA
topped off press 2 during February, although a broom had to stand in for the
traditional tree until an appropriate celebration could be worked into the
schedule.
KBAs
progress in the pressroom can now be followed via The Courier-Journals webcam
at http://webcam.courier-journal.com.
Tony
Smithson is production director of The Courier-Journal, Louisville, Ky.