Tuesday, May 27 was a bright, sunny morning in
Louisville, Ky., when the downtown skyline was suddenly marred by black smoke.
The source of the smoke the new production
facility expansion for The Courier-Journal drew crowds that included
journalists from The Courier-Journal itself as well as reporters from every
television station in town.
Sparks from a grinder had ignited roofing
insulation that had been staged on top of the high bay in preparation for
roofing. Although it looked very bad at the time, the only damage to the
building was the loss of the insulation itself and the metal decking that it sat
on.
No damage
Metallurgical tests conducted on the structural
support beams confirmed that they were not damaged by the heat from the fire. By
re-phasing work, the general contractor was able to respond to the fire and not
lose any time from the project schedule.

A May 27 fire at The Courier-Journals new
production plant had a lot of smoke, but caused little damage.
Photo: The Courier-Journal
Our 15 minutes of fame (or infamy) created by the
fire notwithstanding, the most significant progress during the month was in
exterior finishes and the press table.
The installation of the pre-manufactured external
insulation finish system panels was completed, giving the press bay exterior its
limestone look. The color was a good match with the existing building and
the architectural lines set into the panels echo the block-work on the original
building.
The south face of the building also began to take
shape, with the finish brick going up around the office area. Again, color match
was important, as the bricks sat right against the existing building that stands
on one of Louisvilles main thoroughfares.
Work also started on the visitor parking lot on
the south end of the site. As has been the case during this project, foundations
from long-gone buildings were uncovered and one last underground fuel tank was
discovered and properly disposed.
In addition to the parking lot, the area will
also boast a large landscaped plaza area for the use of employees and visitors.
Press table grows
Inside the building, the press table grew
quickly, despite its complexity. Forty-four columns spread from south to north,
with forms and rebar for the table-top following quickly behind. The table-top
is 18 feet wide, three feet thick and nearly 300 feet long. The amount of steel
rebar in the table is staggering; the steel comprises 14 percent of the tables
volume. An inspection in early June by SLP/Co-Projects, the German engineering
firm retained by (press vendor) KBA North America, confirmed that the steel was
correctly installed and ready for the concrete pour.
Single slab
The press table was poured as a single slab,
using four pumps and a steady stream of concrete trucks. By pouring the slab as
one piece, also known as a monolith, the concrete shrinkage will be uniform
throughout the table, reducing the possibility of cracking.
Looking ahead, as roofs are completed and windows
are installed, the building will be dry and ready for interior finishes. The
month of July will also bring installation of the main power transformers and
switch gear, enabling permanent power to the building.