Although their installation is relatively simple,
the first external insulation finish system panels attached to The
Courier-Journals production facility expansion in downtown Louisville, Ky.,
made quite an impact on the buildings observers.
The panelized EIFS was a perfect solution to the
problem presented by the buildings 80-foot high press bay.
 |
Crews prepare
press table columns on building in downtown Louisville.
Photo: Courier-Journal |
While a press bay clad with sensible aluminum
panels will work in an industrial park, The Courier-Journals historic
location required a finish that approximated the original buildings Indiana
limestone. Color match was important, as was the pattern of reliefs that
mimicked the shape of the limestone blocks.
While exterior finishes are glamorous, the truly
crucial part of the project kicked off in May as well.
Columns poured
The concrete columns for the press table began to
be assembled inside the south end of the press bay as the overhead work headed
north. Ahead of the columns were maintenance rails, roof decking and rain water
leaders that provided the crew with a small measure of protection from the
elements.
The first columns were poured on Friday, May 2,
which in Louisville is better known as Kentucky Oaks Day (the day before the
Kentucky Derby). Despite the fact that both Oaks Day and Derby Day are
considered holidays in Louisville, construction crews made the most of the
spring sunshine.
As the press columns progressed northward, the
forms for the concrete press table were set in place. Because extremely tight
tolerances are required for the press table, an independent survey company was
retained by press supplier KBA to verify the location of key points on the forms
before the tabletop pour.
Framing, sheathing progress
Outside the high bay, activity was brisk as well.
Structural steel columns and beams took on a thick coating of sprayed-on
fireproofing, and on the south face of the building, metal framing and sheathing
went up quickly. A growing crew of masons, meanwhile, built block walls around
locker rooms and maintenance areas.
While the roof decking and exterior walls made
the project look more like a building, it added an additional challenge for the
contractors working inside: the need for lights. A variety of temporary lighting
was strung everywhere from the mailroom ceiling to the stairwells.
Equipment process begins
With the building starting to really take shape,
it was time to get the equipment process rolling. A meeting was held with the
various equipment installers to coordinate equipment arrival and to begin the
complex coordination involved with deploying a large number of systems in a
short time frame.
Representatives of 10 different equipment vendors
joined the contractor and architect to discuss each vendors plans and
requirements well in advance of mobilization.
Indianapolis-based Egenolf Industrial Group will
be the rigger and fitter for the press installation. The KBA Colora will be the
most complex portion of the equipment installation, so other activities,
including the Ferag gripper conveyor installation, will be based on Egenolfs
schedule.